Freedom were working for YEDL in providing Engineering Projects under a Framework Consultancy contract.

Client(s) CE Electric
Location Otley, Yorkshire
Project Start Date October 2003
Project Completion Date July 2004

Freedom were working for YEDL in providing Engineering Projects under a Framework Consultancy contract providing civil design, structural engineering, quantity surveying and project management services.

We acted as project managers during the construction phase of this project supervising YEDL’s civil contractor.

"

We acted as project managers during the construction phase of this project supervising YEDL’s civil contractor.

"

The project involved construction of new replacement substation inc. switchroom, control room, 2 No. built-in Transformers with outdoor cooler compound.

The buildings were constructed in quarried stone & slated pitched roof.

The old substation was demolished & we improved access to a new site road.