Staircase to Control and Battery Rooms Replacement
Client(s): EDF Energy
Our brief was to safely remove the old staircase and remove from site and reinstate with new galvanised stair in accordance with the new fire escape regulations.
Girlington Transformer Replacement
Client(s): YEDL
Freedom was contacted by Yorkshire Electricity Distribution Ltd when a 132/33kV Transformer at Girlington (Bradford) failed in service.
No-Dig Solution
Client(s): EDF Energy (and others)
The project was required in order to eliminate and eradicate ‘cable strikes’ and accidents attributable directly to digging and excavations.
Austin Cannons Grid & Primary Substation
Client(s): EDF Energy Networks
The fencing and security arrangements at Austin Cannons Grid and Primary at Kempston near Bedford were in urgent need of attention.
Site Surveys
Client(s): Various Grid & Primary Sub-Stations
Freedom were tasked with conducting 30 Site Surveys for Central Network over a 6 week period.
Llandudno Promenade
Client(s): Conwy County Borough Council
The Street Lighting Division of NWP Power Systems (part of Freedom) was awarded a contract to refurbish approximately 90 Cast Iron Street Lighting Columns.
Bambers Wind Farm
Client(s): Ecotricity
Freedom was able to call on their vast experience in order to interpret the requirements of the Grid Connection, to design 33kV infrastructure capable of accepting a demand of nearly 10MVA.
Burton Wold 33kV Wind Farm
Client(s): Enercon
The project involved a full turnkey package for the connection of a 20MW wind farm at Burton Wold using 400mm2 Copper conductors, 33KV XLPE single core cables ducted over a route length of 3Km.